Our lot! The beginning
Day 2- 5/19 excavation
Day 3 5/20/15- footers
Day 5 5/22/15- forms placed
Day9 5/26/15- foundation poured
Day11 5/28/15- forms off, waterproofing paint!
Day16 6/2/15 Garage and porch back filled with dirt and gravel in the basement
Day17- lumber and beams delivered
Day19- 6/5/15- basement cement poured
Day20- 6/6/15- first floor framed
Day 21- 6/8/15- second floor framed
Day 22 6/9/15 - roof trusses on and partial roof
Day 23 6/10/15- roof completed